  • 3,300 cubic meters of concrete
  • 448 Metric Tonnes of rebar or 1,000,000 lbs of rebar
  • Equivalent to pour 95 single family house foundations (equivalent to completing a 25 acre single family subdivisions foundations in one day)
  • Concrete temperature of the internal concrete core is expect to reach 65 degrees Celsius.
  • 400 loads of concrete will be delivered
  • Labour / Work force required for the day 140 people
  • 4 concrete pumps with the ability to reach 200 feet
  • Expected concrete volume on site will be 300 cubic meters / hour
  • Concrete pour expected to take 15 hours
  • 3 Concrete suppliers, providing concrete from 5 concrete batching plants in London and periphery area
  • 65 concrete trucks in continuous operation
  • Excavation depth is 38 feet below the surface
  • 130 days of construction preparation to prepare concrete slab